Take a mid-size Dublin basement scheme — roughly 35,000 tonnes of greenfield soil and stone off site. The same material, two legal routes, and a six-figure difference before anyone quotes a gate fee.

The two routes, side by side

Route A — leaves site as waste

Waste recovery levy — 35,000 t × €10€350,000
Facility gate feemarket rate
Haulage — ≈1,167 loads (30 t)distance-dependent
Waste collection permits & facility authorisationsrequired

Levy alone: €350,000 (statutory, S.I. 441/2024).

Route B — registered by-product: €0 levyBY-PRODUCT

Waste recovery levy — material is not waste€0
Gate fee — delivered to a site that wants the filltypically none
Haulage — matched nearby to cut distancedistance-dependent
EPA registration, standstill, SoC + EUDhandled

Levy: €0 — by-product material is not waste, so the levy never arises.

Download this comparison as a one-page PDF →

What a matched movement looks like

The by-product route needs a destination that wants the material. That is the marketplace half of ExchangeEarth: surplus matched to demand nearby, so the haul is shorter and the fill arrives certified — registration reference, Statement of Conformity and End User Declaration attached.

Matched by distance18.6 km

Matches ranked by distance, volume fit, and window overlap.

Straight questions

Is the €350,000 figure real?
It is the statutory levy arithmetic: 35,000 tonnes × €10 per tonne under S.I. 441/2024. Gate fees and haulage come on top of it and vary by facility and distance, which is why they are not quoted here.
Doesn't the by-product route have costs of its own?
Yes — the registration effort, the five-working-day standstill, per-load documentation, and finding a receiving site that wants the material. Those are process costs rather than per-tonne charges, and they are exactly what ExchangeEarth automates and matches.
My muck-away contract already covers disposal. Does this still matter?
The levy is inside your muck-away rate whether it is itemised or not — facilities pass it through the gate fee. On the next tender, a by-product plan is the difference between pricing disposal and pricing haulage only.
What about material that isn't greenfield?
The national criteria route (BP-N002/2024) covers uncontaminated greenfield soil and stone. Other material can still move as a by-product through a single-case Article 27 notification, but the EPA must issue a determination first — a longer, case-by-case path.

General information, not legal advice. Statutory figures only — gate fees and haulage rates are quoted by operators.

How the registration route works, step by step →

Price your next dig on haulage, not disposal.